CoreWeave Denton
Denton, TX | Core Scientific Landlord | OpenAI Customer
12-Month Risk Trend
Monthly scores calculated from weighted factor assessments. Historical data reflects month-end evaluations.
Risk Score Breakdown
Four equally-weighted factors. Workforce and power/grid constraints embedded within. Confidence interval reflects data recency and source reliability.
Score Change Log
Audit trail of risk score changes with rationale. Full derivation notes available upon request.
| Date | Old | New | Change | Rationale |
|---|---|---|---|---|
| Jan 2026 | -- | -- | -- | Monthly review; see RAID log for details |
Contact info@hccouncil.org for detailed factor-by-factor scoring derivation.
Key Risks
CoreWeave operates GPU cloud infrastructure at its Denton, Texas data center through a $12B Microsoft Azure contract. The company raised $7.5B debt financing in 2024, the largest private credit deal for a tech company. CoreWeave filed for IPO in late 2024 with $2B revenue run rate. Core Scientific hosts CoreWeave at its Denton facility under a $6.6B 200+ MW hosting agreement. CoreWeave specializes in Nvidia GPU clusters for AI training and inference, serving OpenAI, Microsoft, and other AI companies. ERCOT grid constraints and Texas power availability remain key infrastructure challenges. (Sources: CoreWeave S-1 Filing; Core Scientific; Data Center Dynamics)
RAID Log
Risk assessments reviewed monthly. Last review: Jan 9, 2026
| Risk | Impact | Probability | Mitigation |
|---|---|---|---|
| ERCOT grid constraints | HIGH | HIGH | Texas power availability limited |
| Customer concentration | HIGH | MEDIUM | Microsoft major customer |
| Nvidia GPU supply | MEDIUM | MEDIUM | H100/Blackwell allocation |
| Action | Owner | Due Date | Status |
|---|---|---|---|
| Core Scientific facility conversion | CoreWeave | 2024-2025 | ACTIVE |
| Nvidia GPU deployment | Operations | Ongoing | DELAYED |
| Power infrastructure upgrade | Engineering | Per phase | ACTIVE |
| Issue | Severity | Status | Resolution |
|---|---|---|---|
| Critical issues | HIGH | ACTIVE | Remediation in progress |
| Decision | Date | Rationale | Impact |
|---|---|---|---|
| Core Scientific partnership | 2024 | Bitcoin miner to AI conversion | 200MW+ Denton facility |
| Microsoft partnership | 2024 | $10B+ compute agreement | Anchor customer for expansion |
Upcoming Milestones
Dates from official company announcements and regulatory filings