Megaproject Risk Monitor

Intel Ohio

New Albany, OH | Advanced Logic

Semiconductor At Risk US Govt 9.9% Stake Intel 14A Process
38
Risk Score (±8)*
*Margin reflects source timing variance
↓ -5 pts YTD
Last Reviewed: May 12, 2026
Reviewed May 12, 2026 Sources: Intel Newsroom Commerce.gov CHIPS Reuters NVIDIA Deal
⚠️ CHIPS Funding Clarification
Ohio receives $1.5B of Intel's total $7.86B CHIPS award. In August 2025, the Trump administration converted remaining federal support into a 9.9% government equity stake ($8.9B) in Intel, eliminating milestone requirements and clawback provisions.
CRITICAL
Original Announcement: January 21, 2022 | Original Target: 2025 | Current Target: 2030-2032 | Delay: 5-6 YEARS | Intel's financial struggles ($18.8B net loss in 2024) have dramatically delayed the project. February 2025 company memo pushed timeline from 2025 to 2030-2032. Only ~$1.5B of $20B invested to date. Ohio's $2B state incentive deadline (2028) conflicts with revised timeline.
$28B
Total Investment
Expanded from $20B (Mar 2024)
Verified: Mar 2024
$1.5B
Ohio CHIPS Award
Of $7.86B total Intel
Verified: Nov 2024
1,500
Ohio Jobs Target
156 current Intel employees
Verified: Dec 2025
2030-31
Fab 1 Target
Fab 2: 2032
Verified: Feb 2025
14A
Process Node
Zero customers
Verified: Jan 2026

12-Month Risk Trend

Monthly scores calculated from weighted factor assessments. Historical data reflects month-end evaluations.

Risk Score Breakdown

Four equally-weighted factors. Workforce and power/grid constraints embedded within. Confidence interval reflects data recency and source reliability.

40
Timeline Adherence
incl. grid queue, permits
Weight: 25%
45
Funding Security
incl. power agreements
Weight: 25%
48
Construction Progress
incl. workforce avail.
Weight: 25%
45
Operator Stability
incl. utility relations
Weight: 25%
📊 Score Derivation Notes (Click to expand)
Timeline (40)
  • Original 2025 target now 2030-31 (5-6yr delay)
  • -25 pts: Original Commitment penalty applied
  • "Go vertical" milestone achieved Q4 2024
  • Ohio 2028 incentive deadline cannot be met
Funding (45)
  • $1.5B Ohio CHIPS (of $7.86B total) secured
  • $8.9B converted to 9.9% govt equity stake
  • Only ~$1.5B of $28B invested to date
  • -15 pts: Funding deployment severely lagging
Construction (48)
  • Site prep complete, "go vertical" achieved
  • 9.4M worker hours logged through 2024
  • Only 156 Intel employees in Ohio (1,500 target)
  • -20 pts: Construction slowed, minimal progress
Operator (45)
  • Intel $18.8B net loss in 2024
  • 24,500 workforce reduction (15%)
  • Zero Intel 14A foundry customers
  • NVIDIA $5B investment provides some stability

Score Change Log

Audit trail of risk score changes with rationale

Date Old New Change Rationale
Jan 2026 38 32 -6 No foundry customer progress; Ohio leadership exodus continues
Sep 2025 42 38 -4 NVIDIA partnership announced (+), but no customer commits (-)
Aug 2025 45 42 -3 CHIPS converted to govt equity; milestone requirements removed
Feb 2025 52 45 -7 Intel memo confirms 2030-31 timeline; 5-6yr delay official
Oct 2024 58 52 -6 $18.8B loss disclosed; 15% workforce cuts announced

Key Risks

Investment Thesis

Intel Ohio was announced as a transformational $20B investment in 2022, later expanded to $28B to establish a leading-edge semiconductor manufacturing hub. However, the project faces severe challenges. The original 2025 production timeline has slipped to 2030-31, a 5-6 year delay. Intel has failed to secure any external foundry customers despite years of effort. The company's financial distress, with significant losses and workforce reductions, raises questions about project viability. The $7.86B CHIPS Act award includes milestone requirements that may not be met, risking clawback. Ohio's lack of semiconductor workforce infrastructure compounds execution challenges. While the strategic importance remains high, Intel's ability to execute is severely compromised.

SOURCES (Click to verify):
Intel Newsroom (Jan 2022) Commerce.gov CHIPS (Nov 2024) Intel SEC Filings CNBC Timeline (Feb 2025)

RAID Log

Severity: HIGH Critical pathMEDIUM ManageableLOW Minor impact

Risk assessments reviewed monthly. Last review: Jan 9, 2026. Sources: Intel Newsroom, Commerce.gov, NBC4 Columbus, Ohio Capital Journal

R
Risks
RiskImpactProbabilityMitigation
Zero Intel 14A foundry customersCRITICALHIGHNVIDIA partnership, aggressive sales
Ohio 2028 incentive deadline conflictHIGHHIGH$2B state package requires renegotiation
5-6 year schedule delayHIGHCERTAINFeb 2025 timeline confirmed 2030-31
Leadership instabilityHIGHHIGH8 Ohio One leaders departed since July 2025
CEO Tan conflict of interest concernsMEDIUMMEDIUMStartup investment controversies ongoing
A
Actions
ActionOwnerDue DateStatus
Site preparation and basementIntel/BechtelQ4 2024COMPLETE
"Go vertical" milestoneIntelQ4 2024ACHIEVED
Government equity conversion ($8.9B)Trump AdminAug 2025COMPLETE
NVIDIA partnership ($5B stake)Intel/NVIDIADec 2025CLOSED
Fab 1 construction completionIntel2030IN PROGRESS
Intel 14A customer acquisitionIntel FoundryOngoingNO PROGRESS
I
Issues
IssueSeverityStatusResolution
Production delayed 5-6 years (2025→2030-31)HIGHCONFIRMEDPer Feb 28, 2025 Intel announcement
Ohio 2028 deadline cannot be metHIGHACTIVERenegotiation with state required
Zero committed Intel 14A customersHIGHACTIVEProject contingent on securing customers
24,500 Intel workforce reductionHIGHCOMPLETE15% cut achieved 2024-2025
Ohio One leadership exodusMEDIUMACTIVEReplacement hiring underway
Only 156 Intel employees in OhioMEDIUMACTIVE1,500 target years away
D
Decisions
DecisionDateRationaleImpact
Select New Albany, OH siteJan 2022$2B state incentives, land availability$20B initial commitment
Groundbreaking with President BidenSep 2022CHIPS Act passage, political supportConstruction began
Expand investment to $28BMar 2024CHIPS Act opportunityTwo-fab Phase 1
Delay production to 2030-31Feb 2025No customers, financial constraints5-6 year delay confirmed
Convert CHIPS to 9.9% govt equityAug 2025Trump admin restructuring$8.9B equity stake
Accept NVIDIA $5B investmentSep 2025Strategic partnership, capital4.5% NVIDIA ownership

Upcoming Milestones

Dates from Intel Newsroom, Commerce.gov announcements, and Ohio state filings

COMPLETE AchievedCONFIRMED OfficialTARGET GuidancePROJECTED EstimateDELAYED Behind
Dec
31
2028
Ohio Incentive Deadline
State requires meeting investment and job commitments by this date. Timeline conflict requires renegotiation.
CONFLICT
Dec
31
2030
Fab 1 Construction Complete
Per Feb 2025 Intel announcement. Building structure and cleanroom installation.
REVISED
Dec
31
2030
Fab 1 Operations Begin
Intel 14A production start, contingent on securing foundry customers.
CONTINGENT
Dec
31
2031
Fab 2 Construction Complete
Second fab shell completion per revised timeline.
PLANNED
Dec
31
2032
Fab 2 Operations Begin
Second fab production start, timeline uncertain.
UNCERTAIN